Client • Wellington Water
Duration • 6 months, 2022
Wellington drinking water Fluoride Upgrade
This project involved work at four water treatment plants. New fluoride dosing containers were installed at the Te Marua and Gear Island Water Treatment Plants. The fluoride dosing systems at Waterloo and Wainuiomata Water Treatment Plants were upgraded.
Stewart Electrical installed fluoride dosing systems, control panels and instrumentation to monitor the fluoride dose rates as part of this work.
The job involved regular liaison with consultants and main contractors to deliver to their requirements and timeframe. This project was delivered on time and to budget.
We continue to provide equipment maintenance services to ensure ongoing the reliability of the fluoride dosing.