Client • Fulton Hogan on behalf of Wellington Water

Location • Te Mārua Water Treatment Plant, Upper Hutt

Duration • 2.5 Years

Te Mārua Optimisation Project

The Te Mārua Optimisation Project involved extensive electrical and control upgrades across multiple treatment processes to improve plant performance, reliability and future capacity.

Stewart Electrical delivered electrical installations and commissioning across numerous plant renewals, supporting one of Wellington's most significant water treatment upgrades.

Project Deliverables

  • CO₂ storage and dosing upgrades

  • Lime silo and control systems

  • POLY/PACL batching and dosing systems

  • Chlorine storage and dosing expansion

  • Caustic dosing upgrades

  • Carbon batching plant

  • Wastewater centrifuge installation

  • Conveyor and load-out control systems